Jambatan Labuan-Sabah

Transparent Progress Tracker

53.3%
Overall Project Completion

Feasibility Study

Completed

Comprehensive study on technical and economic viability of the bridge project

Progress 100%
Target: Jun 2023
Completed: May 2023

Environmental Impact Assessment

Completed

Assessment of environmental impact and mitigation strategies

Progress 100%
Target: Dec 2023
Completed: Nov 2023

Detailed Engineering Design

In progress

Finalization of bridge design specifications and blueprints

Progress 75%
Target: Jun 2024

Land Acquisition

In progress

Securing necessary land parcels for bridge construction

Progress 45%
Target: Sep 2024

Tender Process

Pending

Open tender for main construction contractor selection

Progress 0%
Target: Dec 2024

Construction Phase 1

Pending

Foundation and pier construction

Progress 0%
Target: Jun 2026

Building a better future for Labuan and Sabah

Updates provided by the Labuan MP Office