Jambatan Labuan-Sabah
Transparent Progress Tracker
53.3%
Overall Project Completion
Feasibility Study
CompletedComprehensive study on technical and economic viability of the bridge project
Progress
100%
Target: Jun 2023
Completed: May 2023
Environmental Impact Assessment
CompletedAssessment of environmental impact and mitigation strategies
Progress
100%
Target: Dec 2023
Completed: Nov 2023
Detailed Engineering Design
In progressFinalization of bridge design specifications and blueprints
Progress
75%
Target: Jun 2024
Land Acquisition
In progressSecuring necessary land parcels for bridge construction
Progress
45%
Target: Sep 2024
Tender Process
PendingOpen tender for main construction contractor selection
Progress
0%
Target: Dec 2024
Construction Phase 1
PendingFoundation and pier construction
Progress
0%
Target: Jun 2026
Building a better future for Labuan and Sabah
Updates provided by the Labuan MP Office